Discharge of conditions 39 and 40 on application ref. P17/V0652/FUL
Variation of Conditions 1 (amended parameter plans), 33 (additional land to be included within the Archaeological Written Scheme of Investigation) and 52 (vehicle access) of Planning Permission P13/V1764/O (as amended by letter received 23 March 2017). Outline application for residential development of up to 1500 dwellings including new employment space (use class B1), a neighbourhood centre/community hub (use classes A1, A2, A3, A4, A5, B1, C2, D1 and D2), new primary school, central park, ancillary areas (including allotments and sports pitches) with access off the A338 Grove Road and three accesses off the A417 Reading Road. Provision of a strategic link road between the A417 and the A338 Road to be known as the Wantage Eastern Link Road (WELR). All matters reserved except means of access to the development and the WELR. Additional information received as amplified by agent's covering letter dated 30th October 2013 and agent's e-mail dated 10th December 2013. P17/V0652/FUL Conditions(s) 39 No development shall commence in any phase or sub-phase until a surface
water drainage scheme for that phase or sub-phase based on sustainable
drainage principles and an assessment of the hydrological and hydro-geological
context of the development, as set out in the agreed Flood Risk Assessment ref
50600394 (WSP, 25 July 2013) has been submitted to and approved in writing
by the local planning authority. The scheme shall be in accordance with
requirements of the Sustainable Drainage Design Code (agreed with
Oxfordshire County Council) and the site wide drainage strategy under
condition 6 and shall subsequently be implemented in accordance with the
approved details before the development is completed.
40 No development shall commence in any phase or sub-phase until a drainage
strategy detailing any on and/or off-site drainage works, has been submitted to
and approved by the local planning authority in consultation with the sewerage
undertaker. No discharge of foul or surface water from the site shall be
accepted in to the public system until the drainage works referred to in the
strategy have been completed.