Application registered
Consultation
period
Application under consideration
Decision
made
Description
Installation of 3no. air source heat pumps (Retrospective)
Location
The Gate House Reading Road Upton OX11 9HP
Agent
Anderson Orr Architects Ltd
The Studio 70 Church Road
Wheatley
Oxford
OX33 1LZ
Consultation / Notification
No further Representations on this application will be accepted.
Consultations / Notifications to date are shown below.
Name / Number
Date Sent
Response Date
Upton Parish Council
c/o Liz Cooper - Clerk
41 Dibleys
Blewbury
OX11 9P
Drainage (SouthVale Building Control)
Forestry Team (Vale of White Horse)
25 04 2018
Upton Lodge Cottage
Reading Road
Upton
Didcot
OX11 9HP
Upton Lodge
Reading Road
Upton
Didcot
OX11 9HP
Application Type
Other
(Householder)
Application Progress
Date Received
23rd March 2018
Registration Date
23rd March 2018
Start Consultation Period
3rd April 2018
End Consultation Period
24th April 2018
Target Decision Date
18th May 2018
Decision
Planning Permission on 18th May 2018
Updates
These Planning
Application Details were returned live from our back office database,
and as such are as up to date as when the page was retrieved.