Filling in of voids created from demolition of buildings with demolition materials and 1,000 m3 of material from Harwell site to restore ground levels. Creation of a stockpile with 3,000 m3 of material from Harwell site.
Location
Harwell Sewage Treatment Works Harwell International Business Centre Didcot Oxon
Grid Reference
447917/187705
Agent
Kemp And Kemp
Elms Court
Botley
OXFORD
OX2 9LP
Consultation / Notification
No further Representations on this application will be accepted.
Consultations / Notifications to date are shown below.
Name / Number
Date Sent
Response Date
Health And Safety Executive (HSE) - Northampton
07 03 2005
Peter Dela (Property Services Drainage)
Highway Liason Consultation Form
18 05 2004
Application Progress
Date Received
22nd April 2004
Registration Date
22nd April 2004
Target Decision Date
17th June 2004
Decision
Planning Permission on 17th June 2004