The Abbey Hall is the 1960's building to the rear of the Abingdon Town Council Guild Hall. The Guild Hall is a Grade II listed structure but the Abbey Hall is not considered listed by the incumbent conservation officer. The building has been out of use for the last three years. There is the intention to reopen the Abbey Hall, after a programme of minor refurbishment works which required a review of the means of escape provision to inform the proposal.
The proposed works that require planning permission include:
- the replacement of one emergency escape stair to the Abbey Gate side elevation with a compliant width steel unit, using the existing concrete footings. Style to match existing.
- insertion of an escape stair to the side elevation of the building by the Guildhall car park where previously there was a ramp installed from first to ground level. The proposal is to reinstate the emergency exit door and install a steel framed compliant means of escape stair to ground level.
Location
The Guildhall Abbey Close Abingdon OX14 3JD
Grid Reference
449880/197059
Applicant
Abingdon Town Council
The Guildhall, Abbey Close
Abingdon
OX14 3JD
Agent
Ridge and Partners LLP
The Cowyards
Blenheim Park
Oxford Road
Woodstock
OX20 1QR
Constraints
Abingdon Town Centre Conservation Area
Grade II Listed Building
Consultation / Notification
No further Representations on this application will be accepted.
Consultations / Notifications to date are shown below.
Name / Number
Date Sent
Response Date
Abingdon-on-Thames Town Council
Roysse Court
Bridge Street
Abingdon
OX14 3HU
07 08 2018
Conservation Officer Vale
10 08 2018
Vale - Highways Liaison Officer (Oxfordshire County Council)
13 08 2018
County Archaeologist (VWHDC)
30 07 2018
7 Abbey Close
Abingdon
OX14 3JD
30 07 2018
Application Type
Minor
(Full Application)
Application Progress
Date Received
6th July 2018
Registration Date
24th July 2018
Start Consultation Period
26th July 2018
End Consultation Period
22nd August 2018
Target Decision Date
18th September 2018
Decision
Planning Permission on 17th September 2018