Application registered
Consultation
period
Application under consideration
Decision
made
Description
Discharge of condition 4 - Construction Traffic Management to application P18/V2277/FUL.
Site clearance and preparation, and the development of a Data Centre campus comprising two Data Centre units, emergency back-up diesel generators, the surface storage of emergency diesel fuel, the erection of sub-station, hard and soft landscaping including ecology measures and SUDS, parking and security measures.
Location
Land to the west of Didcot B Power Station
Agent
David Lock Associates
50 North Thirteenth Street
Central Milton Keynes
MK9 3BP
Consultation / Notification
No further Representations on this application will be accepted.
Consultations / Notifications to date are shown below.
Name / Number
Date Sent
Response Date
Oxfordshire County Council Single Response
13 08 2019
Application Type
Other
(Discharge Conditions)
Application Progress
Date Received
30th July 2019
Registration Date
30th July 2019
Target Decision Date
10th September 2019
Decision
Partially Discharged on 2nd September 2019
Updates
These Planning
Application Details were returned live from our back office database,