Planning Application Details

P19/V0913/DApplication Type: Demolition Notif. (Show Map - opens in new window)
Status Bar
 
 Completed stage
 
 Current stage
 
 Next stage
Application registered
Consultation period
Application under consideration
Decision made
Description
The demolition will include the remaining building and structures associated with Didcot A power station. This includes the stack and 3 remaining cooling towers
Location
Didcot A Power Station Purchas Road Didcot OX11 7HA
Grid Reference
450985/192035
Applicant
RWE Generation
Windmill Hill Business Park
Whitehil Way
Swindon
SN5 6PB
Agent
RWE Generation
Windmill Hill Business Park
Whitehil Way
Swindon
SN5 6PB
Case Officer
Adrian Butler
Telephone: 01235 422600
Email: planning@whitehorsedc.gov.uk
Consultation / Notification
No further Representations on this application will be accepted.

Consultations / Notifications to date are shown below.

Name / Number
Date Sent
Response Date
 
Sutton Courtenay Parish Council
c/o Mrs L Martin
Orchard House
90 Howard Cornish Road
Marcham
Abingdon, Oxon
OX13 6PU
 
Appleford On Thames Parish Council
c/o Mrs A Davies
6 Greystones Court
Kidlington
Oxon
OX5 1AR
 
Didcot Town Council
c/o Kathy Fiander
Council Offices
Britwell Road
DIDCOT
Oxon
OX11 7JN
 
Harwell Parish Council
c/o Enborn
Shop Lane
Leckhampstead
Berkshire
RG20 8QQ
 
Milton Parish Council
Joanne Myers
Clerk Milton Parish Council
50 Willow Lane
Milton
Oxon
OX14 4EG
 
Building Control Serv.Manager
 
Countryside Officer(South Oxfordshire & Vale of White Horse)
 
Didcot Garden Town Team
 
Air Quality
 
Contaminated Land
 
Env. Protection Team
26 04 2019
 
Health & Safety Executive (Planning Advice Team)
 
Health & Safety Executive (Hazardous Substance)
 
Environment Agency
 
National Grid Plant Protection
08 07 2019
 
Oxfordshire County Council Single Response
 
SGN Plant Protection Team
02 05 2019
 
National Grid Co Plc
Didcot
OX11 7HH
 
Network Rail
09 05 2019
 
Application Type
Other (Demolition Notif.)
Application Progress
Date Received  
11th April 2019
Registration Date  
18th April 2019
Start Consultation Period  
25th April 2019
End Consultation Period  
11th May 2019
Target Decision Date  
16th May 2019
Decision
Demolition Consent on 14th May 2019
Appeal
No appeal lodged.
Updates
These Planning Application Details were returned live from our back office database, and as such are as up to date as when the page was retrieved.