Application registered
Consultation
period
Application under consideration
Decision
made
Description
Discharge of conditions 3 - Badger protection, 5 - Surface water drainage and 13 - Habitat plan implementation to application P18/V2277/FUL.
Site clearance and preparation, and the development of a Data Centre campus comprising two Data Centre units, emergency back-up diesel generators, the surface storage of emergency diesel fuel, the erection of sub-station, hard and soft landscaping including ecology measures and SUDS, parking and security measures
Location
Land to the west of Didcot B Power Station
Agent
David Lock Associates
50 North Thirteenth Street
Central Milton Keynes
MK9 3BP
Consultation / Notification
No further Representations on this application will be accepted.
Consultations / Notifications to date are shown below.
Name / Number
Date Sent
Response Date
Countryside Officer(South Oxfordshire & Vale of White Horse)
14 11 2019
Application Type
Other
(Discharge Conditions)
Application Progress
Date Received
20th September 2019
Registration Date
20th September 2019
Target Decision Date
13th December 2019
Decision
Fully Discharged on 16th December 2019
Updates
These Planning
Application Details were returned live from our back office database,
and as such are as up to date as when the page was retrieved.