Planning Application Details

P23/V2144/S73Application Type: Section 73 (Show Map - opens in new window)
Status Bar
 
 Completed stage
 
 Current stage
 
 Next stage
Application registered
Consultation period
Application under consideration
Decision made
Description
Variation of condition 3(Temporary) on application P13/V1664/FUL to read "All solar arrays, their supports and foundations; inverters; transformer stations; site substation; access tracks; fencing; and security cameras and their supports; must be removed from the site and the site reinstated to its former arable condition within 12 months or the solar park ceasing to be operational, namely by January 2055. (Installation of ground mounted photovoltaic solar arrays to provide up to 41MW generation capacity together with inverter stations; internal access track; landscaping; stock fencing; security measures; access gate; and ancillary infrastructure).
Location
Landmead Solar Farm Garford Abingdon OX13 5PA
Grid Reference
/
Applicant
Foresight Group
The Shard
32 Bridge Street
London
SE1 9SG
Agent
Murray Planning Associates Ltd
Ground Floor Office
Challenger House
Rumbolds Hill
Midhurst
GU29 9BY
Case Officer
Adrian Butler
Telephone: 01235 422600
Email: planning@whitehorsedc.gov.uk
Consultation / Notification
No further Representations on this application will be accepted.

Consultations / Notifications to date are shown below.

Name / Number
Date Sent
Response Date
 
East Hanney Parish Council
c/o Wendy Quigley
Hanney War Memorial Hall
Brookside
East Hanney
Wantage
OX12 0JL
26 09 2023
 
Drainage - (South&Vale)
26 09 2023
12 10 2023
 
Landscape Architect (South and Vale)
26 09 2023
04 10 2023
 
Natural England
27 09 2023
 
Environment Agency
27 09 2023
 
Oxfordshire County Council - Single Response
27 09 2023
19 10 2023
 
Thames Water Development Control
27 09 2023
05 10 2023
 
Application Type
Major (Section 73)
Application Progress
Date Received  
19th September 2023
Registration Date  
19th September 2023
Start Consultation Period  
26th September 2023
End Consultation Period  
25th October 2023
Target Decision Date  
19th December 2023
Decision
Refusal of Planning Permission on 13th November 2023
Appeal
No appeal lodged.
Updates
These Planning Application Details were returned live from our back office database, and as such are as up to date as when the page was retrieved.