Application registered
Consultation
period
Application under consideration
Decision
made
Description
Following on from previous investigatory works, Noah's Ark 1 Bridge has been assessed and found to substandard (10 Tonnes GVW) in carrying highway loading. This is due to the existing defects observed within the bridge, including several longitudinal/radial cracks running through the arch barrels. The proposed repair and strengthening solution involves an array of radial reinforcement in both orthogonal directions and vertical pins affixed into the soffit (i.e., intrados) of the arch barrel. It is proposed to (1) strengthen, (2) stitch, and (3) carry out traditional masonry local repairs i.e. stonework repairs and repointing to Noah's Ark 1 Bridge, following the defects observed and the structural assessment of the structure.
(Amended Bat Survey received 26 March 2024)
Location
Noah's Ark 1 Bridge Wantage Road, Marcham, Vale of White Horse, Oxfordshire, OX13 5NY
Grid Reference
443768/196150
Applicant
MIlestone Infrastructure
Oxfordshire County Council,
County Hall
New Road
Oxford
OX1 1ND
Agent
MIlestone Infrastructure
Oxfordshire County Council,
County Hall
New Road
Oxford
OX1 1ND
Constraints
Grade II Listed Building
Consultation / Notification
No further Representations on this application will be accepted.
Consultations / Notifications to date are shown below.
If the response has been scanned, you can access the document by clicking the folder icon alongside the relevant consultee. Folders with a
*
alongside them indicate new content within the folders (i.e. new documents added within the last 7 days)
Name / Number
Date Sent
Response Date
Scanned Response
Garford Parish Meeting
c/o Neil Wright
Megstone House
Garford
Abingdon
OX13 5PF
Marcham Parish Council
c/o Mrs L A Martin
Orchard House
90 Howard Cornish Road
Marcham
OX13 6PU
12 03 2024
Heritage Officer (South and Vale)
13 03 2024
Ecology Team (South and Vale)
09 04 2024
Application Type
Other
(Listed Bldg. Consent)
Application Progress
Date Received
22nd February 2024
Registration Date
22nd February 2024
Start Consultation Period
29th February 2024
End Consultation Period
27th March 2024
Target Decision Date
18th April 2024
Decision
Listed Building Consent on 12th April 2024