Council fights to get best outcome for local people as reservoir application progresses

Published 12 November 2026

Vale of White Horse District Council has pledged to continue the fight to get the best outcome for local people as Thames Water’s White Horse Reservoir application is submitted to government next week.

Plans for the controversial reservoir (formally the South East Strategic Reservoir Option or SESRO) near Abingdon have been criticised by local communities, with Vale of White Horse District Council urging water providers to consider alternative solutions more seriously.

Cllr Bethia Thomas, Leader of Vale of White Horse District Council, said: “It is no secret that we have deep concerns for the reservoir and the impact it would have on our district.

“Many questions remain around the size of the proposed scheme, its environmental impact and significant (growing) financial and carbon costs, as well as the potential for increased flood risk in local watercourses.”

The proposal is considered a ‘Nationally Significant Infrastructure Project’, which means it will be determined by the relevant Secretary of State, in this case the Department for Environment, Food and Rural Affairs. The developer must apply to the Planning Inspectorate for a Development Consent Order (DCO) – the stage Thames Water will reach next week.

Cllr Thomas added: “Next week the reservoir reaches a major milestone – with Thames Water submitting an application for development consent to the government.

“In about a month’s time we will know if this has been accepted for examination by the Planning Inspectorate. If it is accepted, we enter a complex pre-examination stage where it is important for the district council – alongside everyone else – to put our view across and make sure local voices are heard.

“We expect to see all the information Thames Water has supplied as part of their application published in early 2027. Up until this point there is still a lot of detail we haven’t seen and need to know. This will all eventually lead to public examination hearings in 2027.”

A proliferation of Nationally Significant Infrastructure Projects (NSIPs)

In October, the council raised concerns about the growing number of Nationally Significant Infrastructure Projects (NSIPs) in the district – alongside the reservoir, with Cearn and Botley West solar farms, the East West Rail proposals and Thames to Southern Transfer. The Botley West solar farm was refused by the Secretary of State on 10 November.

Cllr Thomas reflected: “Potentially, these represent huge changes for the Vale with significant impacts on our communities. We know better than national government what is best for our district – but we have little control in the approval process other than as a statutory consultee. We know that going forwards there is likely to be a substantial increase in the number of projects that will fall under the NSIP umbrella.

“If the Cearn solar farm proposal goes ahead there is a strong possibility that the construction period could overlap with that of the reservoir – with the cumulative impact on local residents a worry.

“I am heartened by the refusal of Botley West solar farm this week as it has shown in this example that the planning process is robust. In the case of Botley West, the needs of the local community and local issues have been taken into consideration, which is exactly what we want to see across all of these major schemes coming forwards in our area.

“We will continue to urge government to listen to local voices and we vow to do everything we can within our power to ensure that the voice of our community is listened to.”

The council has created a new Nationally Significant Infrastructure Projects (NSIPs) hub on its website where people can find out more about these major projects and the planning process. The council will keep the pages updated with the latest developments, including the application status of the reservoir and guidance on how to take part in the examination process.

Examination process

If the application is accepted for examination by the government inspectors, there will be at least four weeks in the process to register as an interested party – which allows for representations in support or objection of the development both in writing and in person at the relevant hearings – and the opportunity to outline any harm that may be caused by the scheme.

The council will also submit a detailed technical report, called a Local Impact Report (LIR) – this is a formal assessment of how the proposed project is likely to affect the area and communities, alongside its own Relevant Representation.

The council will continue to do everything in its power to influence and scrutinise the project to ensure the core issues are addressed, namely major accidents and disasters, flood risk, water quality, nature and biodiversity, construction and traffic impacts, impact on the historic environment and landscape, sustainability/climate resilience and economic and employment commitments.