Details of the scheduled timetable for the Public Inquiry into Thames Water's draft Water Resources Management Plan:
8 December 2009
Inquiry programme start date
2 February 2010
Thames Water and the EA provide a signed statement of common ground
23 February 2010
Thames Water and the EA each provide their statement of case
16 March 2010
All other parties provide their statement of case
14 April 2010
Pre-inquiry meeting between all parties and the Inspector at Cantay House, Park End Street, Oxford
10 May 2010
All parties to submit their proofs of evidence
15 June 2010
Inquiry starts at Cantay House, Park End Street, Oxford – inquiry is estimated to sit for 10 – 12 days